Question : How to set half day rest day on Saturday?
Example:
• Rest day = Saturday (2nd half), and
• Rest day = Sunday (full day)
Answer :
1) Go to Tools>General Maintenance>Calendar (as in Figure 1).
Figure 1
2) Click on Edit (as in Figure 2).
Figure 2
3) Select Advance. Key in the details as in Figure 3 then click on Apply.
Figure 3
If there is any date conflicts with Holiday, choose either it will be considered as rest day or holiday, then click save (Figure 4)
Figure 4
4) Now your company rest day is set. Every Saturdays (afternoon) and Sundays are rest days. Remember click Save to save the setting. (Figure 5)
Figure 5